Cogetinci 2

MOTORWAY: A5 PESNICA – LENDAVA – BORDER H SECTION: LENART – BELTINCI SUBSECTION: COGETINCI – VUČJA VAS KM 3+400 TO KM 12+125

The entire project for the construction of the motorway subsection of Cogetinci-Vučja vas, Phase I, stage 1, NPP 21.20 m runs from km 3+400.00, or passage of the reg. road R3-714, to the border with the neighbouring section of Veučja vas – Beltinci on km 12+124.793. The total length of the motorway route is 8 724.793 m and includes, in addition to accompanying projects, the road part: motorway from km 3+400.00 to km 12+124,793, 30 deviations of existing and newly built roads, temporary connection “Sv. Jurij ob Ščavnici’, road toll station “Dragotinci”
Structures: 3 flat passes, 4 tube passes, 3 underpasses, 6 overstructure, 3 bridges, 3 viaducts – IP, 3 reinforcing walls

Additional information

  • Contracting Authority: DARS
  • Project phase: Basic design, detailed design, as-built design

_IMAGE GALLERY

_see our other projects

Detailed design of cycling track Modrej pri Tolminu

Implementation plan of facilities in the Laško-Celje section