REHABILITATION OF THE CONNECTION BANK AT VIADUCT BORŠT 1, FROM PROFILE P75 TO P79 AT MOTORWAY RAZDRTO-VIPAVA; REBERNICE
In the area of the connection embankment of the support P6, viaduct Boršt 1, visible damage to the left half of the road between the profiles P75 to P79 occurred. As a supporting measure, we have produced a project of an anchored pile wall of 96.6 m in length. Piles with fi 150 with 2.5 m and 3 m are selected. Piles length is from 18.6 m to 13.5 m. Piles are connected to the connecting beam of the indicative dimensions B/H = 190/150 cm. The pile wall is prestressed with 4 cable anchors.
Additional information
- Contracting Authority: DARS d.d.
- Project phase: Basic design, detailed design